New Construction House #129- We are working on completing the interior finish work. The dedication for this home is coming soon! House #135- We are finishing up the siding and the subs have started their rough-in work inside. House #136- Trusses will be installed this week. Once the roof sheathing is installed, it’s on to the front porch, windows, doors, and siding. House #137- Framing is beginning this week. House #138- The city just approved a variance for this corner lot. The building permit will be turned in for review next. House #139- Waiting for building permit approval and ready for the foundation. House #140- Working on the building permit. House #141- Working on the building permit. House #142- Excavation for the foundation is beginning this week.
Renovation Project Houses House #131-134- We are alternating work days at all four of our houses. Two of them are very close to be being completed. We are working with a siding contractor to install new siding on all four of them. |