New Construction House # 135- Subcontractors are completing rough-in work. House # 136- We are finishing up siding and basement framing and preparing for subcontractors. House #137- We are framing the basement structural wall and first floor subfloor before we hand it over to a framing crew. House #138- We are currently digging the foundation. Framing and siding will be completed by subcontractors. House #139- The foundation has been poured. Underground plumbing work is being completed. Framing and siding will be complete by subcontractors. House #140- On hold until Spring 2024. House #141-On hold until Spring 2024. House #142- Basement floor is being poured. Look for framing opportunities coming soon! Renovation Project Houses We are down to the punch list on Houses 133 and 134! These homes will be dedicated on December 9th. House #132 will follow closely behind, and House #131 will be finished in early 2024. |